Master Layout Plan
×
Approvals
Planning Permit No:
PPA / WDCN10/08237/2022
Date of Permit:
2023-01-19
Building Permission No:
BA/WDCN10/00343/2023
Date of Permit:
2023-01-19
Project Update Images
-
-
-
-
- Head room roof shuttering work is in progress.
- 2nd floor block work is completed.
- 3rd floor block work is in progress. (90% completed).
- Terrace Parapet wall brick work is completed.
- Head room roof concrete work is completed.
- 2nd floor block work is completed.
- 3rd floor block work is completed
- 1st floor gypsum plastering work is in progress. (50% completed).
- 1st floor toilet plumbing concealed pipe line work is in progress.
- Staircase flooring work is in progress. (90% completed)
- External plastering work is in progress. (90% completed)
- Stilt floor column and beam plastering work is in progress.
- Lift erection work is completed.
- 3rd floor inner primer coat painting work is completed.
- Door shutter fixing work is completed.
- Terrace floor plumbing ring main pipe line work is in progress. (80% completed)
- External drainage chamber work is in progress. (70% completed)