Contact Us

Ramaniyam Realtors,

14/67, 3rd Main Rd,

Gandhi Nagar, Adyar

Chennai 600 020

+91 4443447500 +91 9710928855 +91 7299922617 sales@ramaniyam.com

Trinity

Thiruvanmiyur

Download Brochure

Download file

Enquire Now

Amenities

Generator Backup
CCTV
Elevators
Rain Water Harvesting

Master Layout Plan

Approvals

Planning Permit No:

PP / HRB / 52 / 2022 / A to B

Date of Permit:

2022-11-30

Building Permission No:

CEBA / WDCN13 / 00375 / 2022

Date of Permit:

2021-12-14

TNRERA:

TN / 29 / Building / 0530 / 2022

Dated:

2022-12-28

Project Update Images

  • Terrace parapet wall brick work is in progress. (75% completed)
  • Staircase wall plastering work is in progress.
  • Lift inner wall plastering work is in progress (50% completed)
  • 6th, 7th, 8th and 9th floor toilet concealed pipe plumbing work is in progress.
  • External plastering work is in progress (20% completed)
  • Terrace parapet wall brick work is in progress. (90% completed)
  • Staircase wall plastering work is in progress. (50% completed)
  • Lift inner wall plastering work is in progress (60% completed)
  • 6th, 7th, 8th and 9th floor toilet plumbing work is in progress.
  • External plastering work is in progress (40% completed)
  • Terrace parapet wall brick work is in progress. (95% completed)
  • Staircase wall plastering work is completed.
  • Lift inner wall plastering work is in progress (60% completed)
  • 7th, 8th and 9th floor toilet plumbing work is in progress.
  • External plastering work is in progress (45% completed)
  • Terrace parapet wall brick work is completed.
  • Staircase wall plastering work is completed.
  • Lift inner wall plastering work is in progress. (60% completed).
  • 7th, 8th and 9th floor toilet plumbing work is in progress. (80% completed).
  • External plastering work is in progress (60% completed).
  • 9th floor toilet plumbing work is in progress. (90% completed).
  • External plastering work is completed.
  • Upto 4th floor general flooring work is in progress.
  • 6th and 7th floor toilet wall tile laying work is in progress.
  • Staircase flooring work is in progress.(80% completed)
  • External plumbing work is in progress. (80% completed)

Property Location

Let your dreams be our

next Project!