Contact Us

Ramaniyam Realtors,

14/67, 3rd Main Rd,

Gandhi Nagar, Adyar

Chennai 600 020

+91 4443447500 +91 9710928855 +91 7299922617 sales@ramaniyam.com

Ocean Dew - Block IV

Pallikaranai

Enquire Now

Amenities

Gymnasium
Elevators
24/7 Power Backup
Lobby
Multi Purpose Hall
Rain Water Harvesting
Playground
Theatre

Master Layout Plan

Approvals

Planning Permit No:

C/PP/MSB/49 (A to F)/2019

Date of Permit:

2019-11-05

Building Permission No:

CEBA/WDCN14/00040/2020

Date of Permit:

2020-01-28

TNRERA:

TN/29/BUILDING/0274/2021

Dated:

2021-09-01

Project Update Images

  • 1st, 2nd, 3rd & 5th floor general flooring and toilet tile laying work is completed.
  • 4th, 6th & 7th floor general flooring and toilet tile laying work is in progress. (50% completed)
  • 8th and 9th floor general flooring and toilet tile laying work is in progress
  • Lift erection work is in progress. (1/3 completed).
  • 3rd, 4th, 7th & 8th floor corridor flooring work is in progress.
  • Staircase 2 Kota stone flooring work is in progress. (50% completed)
  • Swimming pool work is in progress.
  • Rain water Trench work is in progress.
  • Compound wall brick work is in progress.
  • 1st, 2nd, 3rd, 4th & 5th floor general flooring and toilet tile laying work is completed.
  • 6th & 7th floor general flooring and toilet tile laying work is in progress. (50% completed)
  • 8th and 9th floor general flooring and toilet tile laying work is in progress
  • Lift erection work is in progress. (1/3 completed).
  • 4th, 5th, 6th,& 10th floor corridor flooring work is in progress.
  • Staircase 2 Kota stone flooring work is in progress. (60% completed)
  • Swimming pool work is in progress.
  • Rain water Trench work is in progress.
  • 1st, 2nd, 3rd, 4th & 5th floor general flooring and toilet tile laying work is completed.
  • 6th & 7th floor general flooring and toilet tile laying work is in progress. (50% completed)
  • 8th and 9th floor general flooring and toilet tile laying work is in progress
  • Lift erection work is in progress. (1/3 completed).
  • 4th, 5th and 6th floor corridor flooring work is in progress.
  • Staircase 2 Kota stone flooring work is in progress. (70% completed)
  • Swimming pool work is in progress.
  • 1st, 2nd, 3rd, 4th & 5th floor general flooring and toilet tile laying work is completed.
  • 6th & 7th floor general flooring and toilet tile laying work is in progress. (70% completed)
  • 8th and 9th floor general flooring and toilet tile laying work is in progress
  • Lift erection work is in progress. (1/3 completed).
  • 4th, 5th and 6th floor corridor flooring work is in progress.
  • Staircase 2 Kota stone flooring work is completed
  • Swimming pool work is in progress.
  • Rain water Trench work is in progress.
  • Upto 11th floor inner wall primer coat painting work is completed.
  • Upto 10th floor Kitchen and Counter platform wood work is completed.
  • Lift erection work is in progress. (1/3 completed).
  • External Paving block work is in progress (40% completed).
  • 6th & 7th floor general flooring and toilet tile laying work is in progress. (70% completed)
  • 8th & 9th floor general flooring and toilet tile laying work is in progress.
  • Lift erection work is in progress. (1/3 completed).
  • All floors corridor flooring work is completed.
  • Staircase 2 Kota stone flooring work is completed.
  • Swimming pool work is in progress.
  • Rain water Trench work is in progress.
  • Compound wall brick work is in progress.